Investigation identifies oxidiser-pump electrical and thermal failures behind Eris maiden-flight loss
70 FOMOThe investigation established that two of Eris's four first-stage hybrid motors suffered thrust losses during the July 2025 flight. The first malfunction occurred approximately nine seconds after ignition and another appeared around 17 seconds. Both failures originated in the oxidiser pump subsystem, with electrical and thermal faults identified in motors and inverters. Gilmour said design, qualification and process improvements were being evaluated and implemented, and submitted its final report to Australian regulators.
Why it matters
The identification of specific failure modes provides a concrete engineering basis for corrective action. The upgraded Sirius engine firing in August 2026 subsequently provided an important validation milestone, although integrated flight performance remains unproven.
The numbers
Coverage
-
Gilmour Space ·
Update on Eris TestFlight1 InvestigationGilmour Space published the findings of its investigation into the failed Eris TestFlight1 mission of 30 July 2025. One of the four first-stage hybrid engines lost thrust approximately nine seconds after ignition, followed by a similar problem in another engine around 17 seconds. Investigators identified two independent failure modes involving electrical and thermal faults in the oxidiser pump subsystem, including electric motors and associated inverters. A final report was submitted to the Australian Space Agency and Office of the Space Regulator.
AI-assisted summary of 1 report; numbers link to their source. Spot an error? Tell us.
More from Gilmour Space Technologies
- Gilmour Space Technologies · Partnership 42
Gilmour Space and Hypersonix establish sovereign hypersonic flight-test partnership
- Gilmour Space Technologies · Test fire 60
Upgraded 110 kN Sirius engine completes 116-second mission-duration hot-fire
- Gilmour Space Technologies · Milestone 21
Former NASA Deputy Administrator Pamela Melroy joins Gilmour Space's board
- Gilmour Space Technologies · Partnership 49
Gilmour Space selected as Starfish Space's Otter Pup 2 docking partner
- Gilmour Space Technologies · Milestone 6
Gilmour Space establishes a South Australian representative office at Lot Fourteen
- Gilmour Space Technologies · Partnership 27
Gilmour Space partners with Transcelestial for satellite laser communications
Related moments
- iSpace (Interstellar Glory) · Other 49
Hyperbola-3 interstage and aft thrust structures pass static load testing
- iSpace (Interstellar Glory) · Other 64
Hyperbola-3 methane and common-bulkhead tanks pass ultimate-load structural tests
- iSpace (Interstellar Glory) · Test fire 58
Hyperbola-3 first-stage auxiliary propulsion system passes full-system test
- iSpace (Interstellar Glory) · Other 58
Hyperbola-3 second-stage common-bulkhead tank passes cryogenic static testing
- iSpace (Interstellar Glory) · Test fire 70
Focus-2 methalox engine completes flight-configuration matching test with Xingkong-3 control system
- Astro Mechanica · Other 60
Astro Mechanica outlines 2026 ground-testing plans for its hybrid-electric supersonic engine
Veenie.Space Telemetry
The investigation established that two of Eris's four first-stage hybrid motors suffered thrust loss